Manage multiple resource requirements
Overview
If your organization has the Multiple resource requirements (MRR) feature enabled, you can specify multiple groups of resources and required tags for each work item. This feature can be useful when you need to specify different tags for different stages of a work item.
For example, you may need to specify that a work item requires one set of tags for the first two hours and then a different set of tags for the remaining six hours.
Important
The Multiple resource requirements feature must be enabled by an administrator before it can be used. Contact your Skedulo Customer Success Manager to request access to this feature.You can use optimization to allocate work with multiple resource requirements provided the work item has a set time.
A quick way to tell if the Multiple resource requirements feature is enabled for your organization is to open a work details page and look at the Resources column. If you see Add another requirement, then the feature is enabled.
Caution
Adding multiple resource requirements to jobs created before the Multiple resource requirements feature was enabled may cause complications. Schedulers are warned that this action might activate custom triggers in Salesforce (if configured by their organization), allowing them to take appropriate action.Known limitations
The following features are not supported when the Multiple resource requirements feature is enabled:
- The Suggest feature is disabled on both the Schedule tab of the work details page and the Work list in all consoles.
- Allocate job from Recurring Schedule view. The Allocate button is unavailable.
- Reschedule a job.
- Restore a canceled job.
- Use the job swap feature in the Skedulo v2 mobile app.
Add additional resource requirements when creating a work item
Schedulers can add multiple resource requirements when creating or editing a work item.
When creating a work item
- On the Create job page, select the Requirements tab.
- Click Add another requirement to add additional resource requirements.
- Set the quantity of resources and skill tags for each requirement.
When editing a work item
- Open a work item to display the work details page.
- In the Resources section of the Details tab, click Add another requirement.
Delete additional resource requirements
When creating a work item
- Click the x on the resource requirement group you want to delete.
When editing a work item
- Click
Actions on the resource requirement group you want to delete and select Delete requirement.
Feedback