Understand job start and end times calculations

Understand how the job start and end time fields work in Skedulo.

Overview

A job has six start and end time fields. The table below shows when each field first gets a value and when the value changes.

Field Description
Start The planned start time. It changes when the job is rescheduled.
End The planned end time. It changes when the job is rescheduled or its duration changes.
Estimated Start Populated when the job is allocated, based on the Start time. Updated when the job is rescheduled. Updated when the job is set to “In Progress.” Updated when the job is set to “Complete.”
Estimated End Populated when the job is allocated, based on the End time. Updated when the job is rescheduled. Updated when the job is set to “In Progress.” Updated when the job is set to “Complete.”
Actual Start Populated when the job is set to “In Progress.”
Actual End Populated when the job is set to “Complete.”