Job start and end times

The start and end time fields on a job, and when each field is set and updated.

Job times

A job has six start and end time fields, listed in the table below.

Field Description
Start The planned start time. It changes when the job is rescheduled.
End The planned end time. It changes when the job is rescheduled or its duration changes.
EstimatedStart The estimated start time. See Understand job start and end times calculations for when it is set and updated.
EstimatedEnd The estimated end time. See Understand job start and end times calculations for when it is set and updated.
ActualStart Populated when the job is set to “In Progress.”
ActualEnd Populated when the job is set to “Complete.”